A 500-acre data center campus proposed on farmland outside Yerington has advanced over the objections of about 200 residents who showed up to oppose it.
LYON COUNTY
The Lyon County Board of Commissioners has advanced a permitting request from Copia Power for the Monarch Data Center Campus, a proposed development on 500 acres of farmland just outside Yerington in Mason Valley. About 200 residents attended the commission meeting where the request was considered, with most speaking in opposition.
Copia Power permitting manager Michael Paul described the area as an energy hub for the project. Separately, developer Tract has acquired more than 1,000 acres elsewhere in Lyon County, though that acquisition has not been publicly tied to the Monarch proposal.
Residents who oppose the project cited the area’s agricultural history and concerns about water and power consumption. Yerington resident David Janakos spoke against the development at the commission meeting. Landowner Brian Masini, in a letter to Lyon County Commissioner David Hockaday, wrote that farming is no longer economically viable in Mason Valley, a view that runs counter to much of the opposition’s framing.
Lyon County Manager Andrew Haskin cited the industrial tax revenue the project could generate for the county. Doug Busselman of the Nevada Farm Bureau said data center development should be designed to fit the community it’s built in, while Fred Steinmann of the University of Nevada, Reno’s Center for Economic Development said growth of this kind does not automatically pay for itself in public benefits. Patrick Donnelly of the Center for Biological Diversity criticized developers for targeting small rural communities with large-scale projects.
Nationally, data centers used an estimated 17.43 billion gallons of water in 2023, according to a 2024 University of California, Berkeley report, which projected that figure could roughly double by 2028. By comparison, American agriculture used 81 million acre-feet of water in 2023 — more than 26 trillion gallons — according to the U.S. Department of Agriculture. NV Energy has acknowledged it does not yet have enough power capacity lined up for the data centers already planned in Nevada.
The Walker River Substation, part of the Greenlink transmission project, is under construction about two miles from the proposed site, alongside planned 400-megawatt solar and 400-megawatt battery storage projects.
Sources: Lyon County Board of Commissioners hearing and permitting record on the Monarch Data Center Campus; statements by Copia Power’s Michael Paul, Lyon County Manager Andrew Haskin, Nevada Farm Bureau’s Doug Busselman, UNR Center for Economic Development’s Fred Steinmann, Center for Biological Diversity’s Patrick Donnelly, and residents David Janakos and Brian Masini; 2024 University of California, Berkeley report on data center water use; U.S. Department of Agriculture 2023 agricultural water use data.